Workplan for project year 1

Activities Total duration (number of weeks) M10 M11 M12 M01 M02 M03 M04 M05 M06 M07 M08 M09
Ref.nr/ Sub-ref nr Title
WP1 A1.1 Kick off meeting 1   x                    
WP1 A1.2 Workshop on project management 1   x                    
WP1 A1.2 Baseline Study 7   x x X                
WP2.1. A2.1.1 Seminar on results of Baseline Study 1       X                
WP2.1. A2.1.2 Establishment of T2Ps 4       x X              
WP2.1. A2.1.3 Study visits of T2Ps coordinators to international partner HEIs 1         X              
                             
  A2.2.1 Organization of 2 capacity building workshops with international experts 2         x x            
WP2.2. A2.2.2 Organization of 6 capacity building workshops for transferring the knowledge to partner HEI 3           x            
WP2.3. A2.3.1 Conduct of field research and development of case studies 24             x x x x x X
WP3. A3.1 Quality Monitoring Plan 48 x x x x x x x x x x x x
WP3. A3.2 Meeting of the Committee for Quality Assurance 1     x                  
WP3. A3.3 Obtaining National Accreditation 40     x x x x x x x x x x
WP4. A4.1 Communication Strategy development 3 x X                    
WP4. A4.2 Project Brand and Marking Plan development 4     x                  
WP4. A4.3 Online Platform developed 4     x                  
WP4. A4.4 Organization of promotional and informative events 20               x x x x x
 WP5. A5.1. Project management team establishment andcreation of the project working documents  1    X                    
WP5. A5.2 Meetings of the project team 48 x x x x x x x x x x x x
WP5. A5.3 Project finances and administration 48 x x x x x x x x x x x x
 WP5. A5.4 Development and adhering to internal managementprocedures  48  x  x  x  x  x  x  x  x  x  x  x  x